Start Mind Mapping Now!
- Professional Mind Mapping
- Best MS Office Integration
- Build-in Gantt chart & Timeline
- Templates & Tutorials
Construction Project Plan - Gantt Chart

- Construction Project
- General Conditions
- Receive notice to proceed and sign contract
- Submit bond and insurance documents
- Prepare and submit project schedule
- Prepare and submit schedule of values
- Obtain building permits
- Submit preliminary shop drawings
- Submit monthly requests for payment
- Site Grading and Utilities
- Clear and grub site
- Install underground utilities
- Install temporary power service
- Install exterior fire line and building fire riser
- Erect building batter boards and layout building
- Foundations
- Excavate foundations
- Excavate elevator pit
- Form column piers and spread foundations
- Rough-in electric and plumbing in elevator
- Form elevator pit walls
- Pour column piers, foundations and walls
- Cure
- Strip forms
- Install pneumatic tube in elevator pit
- Prepare and pour concrete floor in elevator pit
- Steel erection
- Erect steel columns, beams and joist - 1st and 2nd floors
- Erect steel columns, beams and joist - 3rd floor and roof
- Install miscellaneous iron and bracing - 1st and 2nd floors
- Install miscellaneous iron and bracing - 3rd floor and roof
- Install stairs and miscellaneous iron railing
- Touch-up paint on steel
- Form and Pour Concrete - Floors and Roof
- Install rebar and in-floor utilities (including mechanical, electrical, plumbing)
- Pour separate floors
- Cure separate floors
- Strip forms
- Form roof slab including all floor openings
- Install electrical underground
- Install plumbing underground
- Install rebar and in-floor utilities
- Masonry Work
- Rough-in plumbing at toilets and masonry walls
- Lay masonry at core, mechanical, and toilets
- Install exterior masonry work
- Install roof drains
- Install tile in toilet rooms
- Roofing
- Install flashing at parapet walls
- Pour lightweight concrete roof fill
- Install seamless roofing material
- Spread stone ballast on seamless roof
- Set rooftop equipment
- Building Finishes
- Install millwork and wood trim
- Paint walls and woodwork
- Install conduit at ceiling plenum space
- Install duct in ceiling plenum space
- Install ceiling grid
- Install ceiling tile
- Hang wallpaper
- Install building carpet
- Install hardware and accessories
- Complete interior and exterior sod and plantings
- Pave, curb, and stripe parking lot
- Plumbing
- Rough-in plumbing in drywall walls
- Tie-in fire line riser and set valves
- Set plumbing fixtures and trim
- Flush, test, and clean piping and fixtures
- Electrical
- Rough-in electrical in masonry walls
- Rough-in electrical in drywall walls
- Pull wire in conduit and set area transformers
- Install and terminate electrical devices
- Make electrical terminations for HVAC equipment
- Heating and Ventilating - AC
- Set equipment in mechanical room
- Rough-in mechanical in masonry walls
- Rough-in mechanical in drywall walls
- Install duct in building chase
- Install light fixtures - test and clean
- Complete Final Inspections
- Complete elevator inspection and certification
- Perform architect's inspection
- Perform local building agency inspection
- Perform Fire Marshal's inspection
- Final Clean-up and Occupancy
- Install hard tile flooring in common areas
- Clean hard tile floors
- Remove debris from building and do final clean-up
- Substantial completion date
- Complete punch list items from all inspections
More Maps by This User