  • Open New Line In McPherson
    • Planning
      • Design All New Parts
      • Order Materials
        • Find Locations for all new Materials
      • Create Work orders
    • Begin First Assembly
      • Open all Lowest level work orders for a Quantity of 1
      • Open higher level work orders as lower levels are complete
      • Construct all necessary tooling
    • Put together first assembly
      • Ensure more workers learn process
      • Troubleshoot and Order any new materials needed
      • Finish assembly and ship
    • Get all assemblies to McPherson in time for new line open
      • Open work orders for remaining assemblies in staggered pattern every other month
        • Schedule Overtime accordingly
      • Give locations to all new parts and store until use
      • Ship all assemblies to McPherson on dedicated truck